Please note that VisualCron support is not actively monitoring this community forum. Please use our contact page for contacting the VisualCron support directly.


adminESD
2011-06-06T13:50:14Z
Hi all,

I have a task with different sub-task which are totally independant each from others.
I'd like to know how to configure conditions in order to let continue VisualCron to run the second task when the first one failed.

Thank you for your help.
Sponsor
Forum information
cmagnoc
2011-06-06T14:51:45Z
Hello,

We use the same function here with version 5.7.4 buid 26370 and we solved this problem settgin the option "continue to the next Task in order" on tab "on error".

I hope this help you.

cmagnoc
adminESD
2011-06-06T15:54:16Z
Thank you very much, it's exactly what i was looking for.
2026-10-19T08:21:35Z
Paris Hilton: So lovely spending time with Manny and h nusahoki 
2026-10-21T13:12:34Z
You made some decent points there. I looked on the net for your problem and located most people goes together with along with your internet site. olxtoto
Scroll to Top